Red Scar Business Park

Red Scar Business Park

Green Frog Connect carried out an essential 2km 33kV high voltage cable infrastructure installation at this site just off junction 31A of the M6 to connect a 40MW embedded gas peaking power plant to an existing 33kV electricity substation. Read more

Submeadow grid connection

Sudmeadow Road Gas-fired Generation Plant

This brownfield site in Gloucestershire was constructed in one phase and has its’ own 33kV connection to Western Power Distribution. With a total site export capacity of 40MW, the gas-fired generation site has its own connection to the local High Pressure (HP) gas network. Read more

Viridis 178 Projects

Green Frog Connect are the appointed ICP for Viridis 178, working together to design and build in excess of 200MW of embedded gas generation back up power for the National Grid from now until 2018 Read more