Rodbourne Rail Solar Farm

Green Frog Connect was the appointed Independent Connections Provider for this solar farm development, which was completed in May 2013 and provides sufficient power for 1,970 homes.

Solar panel
Location: Malmesbury, Wiltshire
Capacity: 7.6MW
Project length: Two months
Client: British Solar Renewables

Key client benefits

  • Design approval and energisation was achieved in only two months allowing the client to meet their ROC deadline.

Project details

A 7.6MW solar park, this project was connected to the local 33kV network via teed connection 500m from the site. The substation building provided was of GRP construction. Our services comprised:

  • Design, project management and construction for the new contestable works
  • Installation of 33kV metering substation
  • Associated jointing, excavation and cable pulling works
  • Project Management of non-contestable works