ICP works for Green Lane Sawmills

Green Frog Connect completed the Independent Connection Provider (ICP) works for M. H. Southern & Company’s new production facility and sawmill, creating significant cost and time savings through negotiating an Independent Distribution Network Operator (IDNO) solution that also allowed for flexibility in the design. Read more

132kV connection for Air Liquide

Green Frog Connect successfully installed a new 20MW 132kV connection, enabling the Air Liquide’s business-critical factory upgrade to go ahead. Read more

Rising to the challenge

We’ve just completed our latest connection to a private wire solar project, designed to supply an existing industrial client. Read more

Red Scar Business Park

Green Frog Connect will be carrying out essential high voltage infrastructure installation to be connected to Electricity North West Limited’s primary substation in Preston East (off Bluebell Way, opposite the Premier Inn hotel). Read more

Red Gap Moor Wind Farm grid connection

Red Gap Moor Wind Farm

Green Frog Connect acted as the Independent Connection Provider for this 12.5MW wind farm generation plant, undertaking the design and construction of the electricity grid connection contestable works. Read more

Submeadow grid connection

Sudmeadow Road Gas-fired Generation Plant

This brownfield site in Gloucestershire was constructed in one phase and has its’ own 33kV connection to Western Power Distribution. With a total site export capacity of 40MW, the gas-fired generation site has its own connection to the local High Pressure (HP) gas network. Read more