Green Frog Connect were appointed to provide the contestable design works for this 11kV wind turbine development, which was completed in September 2013.

Wind turbine
Location: Anglesey
Capacity: 500kW
Project length: Four months
Client: Livos Energy

Key client benefits

  • Project connected on time to allow the client to meet their feed in tariff deadline.

Project details

Our services comprised:

  • Design, project management and construction for the new contestable works.
  • Installation of 11kV metering substation.
  • Associated jointing, excavation and cable pulling works.