We are acting as the principal contractor as well as the Independent Connection Provider for a new gas-fired power generation site at Swansea West.

Location: Swansea West
Capacity: 40MW
Project length: Seven months
Client: Green Frog Power
Key client benefits
- We designed and negotiated a simplified connection arrangement which saved the client in excess of £500k compared to their original arrangement.
- We diverted a private overhead line that was originally routed through the site and managed all outages to ensure that the businesses being fed did not lose supply.
- A shared electricity and gas trench for the off-site connections was coordinated to minimise costs and reduce the amount of disruption to the local community.
Time-lapse of site build
Click here to watch the site develop on Youtube.